standardised monitoring plans
faqs
 
Your questions answered
How does the approach encourage use of the ‘outputs’ based approach identified as the preferred approach by the DfT publication “Using the Planning Process to Secure Travel Plans”?

The 'bigger picture' need for the standard is that it clearly sets the output required for the travel plan at an early stage in the TA negotiation process. This will help reduce the commonly problem of optimism bias of the impact of the travel plan.

The focus on outputs will help address the problem of over-promising and under-delivering. It will concentrate minds on what is practicable and achievable. It will help address the common use of optimism bias to avoid the costs of expensive mitigation measures or potential refusal of permission.

The lack of a nationally recognised mechanism through which outputs can be fairly and transparently measured, independent from the local authority or the developer, has up until now been a the main barrier to the roll out of the preferred ‘outputs’ based approach.



This procedure refers to pre-existing operations where a Travel Plan is to be implemented. We suggest that this a relatively limited occurrence, as the imposition of planning obligations to prepare a Travel Plan would generally arise only where there is a significant change from the pattern of the operation such that direct surveys of the baseline may not be relevant.

It is likely to be a limited occurrence. For example, it may be appropriate for expansions of existing sites where it would be helpful to extrapolate trends.


The guidance states that the survey must be commissioned by an appropriate local authority and be carried out by an approved independent specialist survey organisation. Consultants would already be employed by the “developer” who will have invested knowledge of the site. Surely they will be best placed to scope the appropriate surveys and will allow the client to ensure that he has best value?

It can be difficult to obtain permissions to visit sites, etc and in some cases it may be easier to use the existing consultants. However it is equally important that the organisation undertaking the survey is seen to be acting impartially and the risk of client pressure needs to be ‘managed out’ as far as possible.


There is an implication in this requirement that any incumbent consultancy organisation may distort the survey design or result to benefit the developer.

The approach is intended to ensure that the organisation undertaking the survey is seen to be acting impartially and the risk of client pressure is ‘managed out’. Consultants acting on behalf of the developer can find this difficult and this approach therefore helps to establish a more transparent approach.


Surely this is an unnecessary restraint on the developer’s freedom to employ his chosen advisers?

There is no restraint on the developer to employ his chosen specialists to help develop the transport strategy. The approach simply proposes that the survey process for proving that the organisation has met their travel plan targets has undertaken independently.


Why isn’t it sufficient to agree with the local authority the scope of survey and reporting in relation to any standard data formatting requirement?

The standardised approach recognises local authority concerns that negotiation of survey scope on a site basis is an inappropriate use of limited local authority resources. It also leads to a plethora of different approaches to surveys that make the data difficult to compare and inform decision across the county.


In many cases a developer’s operational travel and transport patterns will contain elements which are commercially confidential. Would they be prepared to share these issues on a wider basis or to have them under the control of the local authority where they could be subject to the Freedom of Information Act?

The standard approach does not require data of a commercially sensitive nature. It is monitoring to assess whether the organisation /developer has met their targets as detailed in their TA and travel plan. Copies of these documents are already available to the public.

The survey is simply demonstrating that the organisation has met their travel plan obligations detailed as part of the s106 agreement. It is in the public interest to demonstrate that they have met their obligations and we see no reason why this information should not be made publicly available.



It is already possible for the relevant officers to view information to confirm compliance with travel plan targets and there is nothing to stop the local authority making independent observations, so why the need for this standard?

The system makes best use of limited local resources to confirm compliance with targets using an independent approach to monitoring. It will reduce ambiguity in the statistical robustness of the data and streamline the decision making process.


The document refers to surveys in the format of the TRICS® multi modal survey. Surely survey techniques should be issued which are appropriate to the situation, rather than a fixed regime?

The TRICS® multi modal survey has sufficient flexibility to respond to most survey requirements. The use of the system as the industry standard for informing trip rate calculations is already nationally recognised. The use of the system as the industry standard for collating monitoring data will help provide more trip rate information that will in turn speed up the process of agreeing appropriate trip rates for sites with effective travel plans in place.



Will the introduction of the standard require greater expenditure?

No. The standard taps into an existing financial commitment and will not involve significant additional costs to most.

Developers already have to collect monitoring information so the standard does not create a need for new expenditure. It simply consolidates all data in one place so that it is more accessible.



Any consultant of repute will have in place their own management systems to validate the surveys to ensure that they meet the required quality standard. Won’t developers feel that this represents additional costs?

Local authorities currently have to assess a wide variety of surveys from a broad range of consultants. The local authority has no influence on a developers’ decision to assign a ‘consultant of repute’.

Surveys previously submitted to the local authority vary widely in quality. The standard approach will set a de minimus quality level that is fair and transparent for all applicants. It is unlikely that the introduction of this standard will place additional requirements on so called ‘consultants of repute’ as they are already likely to meet or exceed these minimum standards.

The survey requirements are already part of the generally accepted cost of development applications. Using the standardised approach the costs are more transparent as part of the development process. This is something which the greater proportion of developers will appreciate.

Validation cost is likely to be small. The fact that it is undertaken by an independent 3 rd party will help to expedite the planning decision process. It is hoped that the reduction of ambiguity in the planning process will minimise the need for complex technical negotiations and introduce economies to the benefit of the applicant compensating for the cost of the validation.


In our experience, there is a great deal of information held within consultancies which will already allow robust estimates of travel plan impacts to be determined.

The information held by consultancies is of varying quality and statistical robustness. Since the data it is frequently not subject to independent validation local authorities often express reservations in accepting the data as the basis for trip rate calculations and travel plan targets.


We agree that it should be the role of the local authority to validate and agree trip generation estimates and targets although shouldn’t this be as part of the overall scoping approval of the transport assessment?

This will continue, however the negotiation process should be less protracted.


In our experience a regime for monitoring the effectiveness of the Travel Plan is best built into the planning approval process or associated legal agreements. Doesn’t that give a robust basis for subsequent monitoring?

Most effective travel plans are secured through the planning process and associated legal agreements. However many developers or their occupiers find the process of ‘signing off’ the travel plan commitments upon meeting their targets complex and protracted. Frequently this is because of ambiguity in the statistical robustness of the monitoring survey. We feel that it is therefore important to set out requirements that will standardise this process to make it fair and transparent.


The guidance indicates that the initiatives and measures should be recorded using the new “Travel Plan Record Sheet” which forms part of the TRICS® multi-modal survey. It is not clear from the documentation whether the record sheet and survey documentation will be issued to use free of any copyright restrictions?

TRICS® have been piloting the travel plan record sheet on a first round of trial sites. Once these record sheets have been tested they will be made available on the TRICS® website for download, anticipated to be summer 2006.


Will the ‘after’ survey be a repeat of the before survey?

This is mainly the case for local authorities wishing to use the standard approach of assessing the impacts of travel plans for a local accreditation scheme. As explained in the leaflet most travel plans are secured through the planning process. They are usually subject to a TA and usually do not lend themselves to before studies.


Surely the inherited knowledge of an incumbent consultant is especially valuable in scoping, implementing and understanding the after surveys?

The scope of the travel plan is still agreed during the planning process. The standard approach will be used to assess independently whether the developer /occupier has met the targets set in their legal obligations.


Why would we need an independent summary report to be produced by TRICS®?

This option is offered in response to local authority requests for an independent body to assist in resolving complex disputes.



What is the relationship between TRICS® and JMP?

JMP are the current contractors appointed by competitive tender to manage and market the TRICS® system on behalf of a consortium of local authorities. Trics have instructed jmp to develop this facility in response to requests from members to make available such a service.


The document states that the guidance is not compulsory although local authorities are making it standard in all planning applications and travel plans. Have the public and private sectors affected by the guidance been consulted?

We have embarked on an extensive programme of research, development and consultation on the standard approach to monitoring travel plans over the past 3 years.

However all feedback is appreciated and has helps us to understand the further communication that will be required to clarify common points of confusion regarding the standard approach.



How will this system derive benefits?

The TA frequently asserts that the Travel Plan (TP) will be implemented to achieve reduced trip rates. The standard approach measures the 'output' of the combined TA /TP.

Government are concerned that the traffic generated on the highway network is greater than that anticipated through approved TA’s. This is exacerbating congestion on the network.

This approach will evaluate whether the development met it trip rate and mode share targets it alluded to in the original TA. Planning obligations can then be signed off in the knowledge that the requirements have been met.

In measuring the output of the transport strategy implemented the standard will also collate useful information about the measures introduced, which can be used to inform future development planning decisions.



Will developers at TA stage be prepared to undertake a TRICS® quality survey?

We do not necessarily expect developers to undertake a TRICS® quality survey at a TA stage as standard. The only real need for a new TRICS® survey to be undertaken by a developer prior to their application is if there is insufficient data currently available as is currently the case.

The 'before' baseline in most cases is generated by the TA which commonly uses TRICS® to help determine an appropriate trip rate & mode share.

An increasing number of S106 agreements require targets to be met. The standard approach simply requires that the assessment of whether targets have been met, is undertaken using a consistent national standard developed by TRICS®.



How frequently should surveys meeting the national standard be undertaken?

The process is intended to measure the transport impacts of a TA and Travel Plan strategy. At present many authorities only require the assessment survey to be completed once following a period of occupation and travel plan implementation, generally 3 to 5 years after initial occupation. However, it is now becoming the norm for significant development sites to engage in a regular process of assessment (every 3 to 5 years) for perpetuity. This is to ensure that the site transport requirements are continually revisited by the site occupiers and travel demands effectively managed to stay within the footprint originally agreed through the TA.


Why don’t we use the survey results collated by the site occupier?

In order for an organisation to meet their TP targets it is likely that they will have to undertake regular monitoring of their own to inform the development and successful implementation of their TP. On average these surveys achieve a 20-40% maximum sample size.

This causes many arguments about statistical robustness when organisations attempt to sign off their S106 requirements with the local authority and unnecessarily sucks in limited resources to arbitrate.

The standard approach will achieve close to 100% of the sample and therefore be a more accurate assessment of whether they have met their targets. This reduces ambiguity and focuses efforts on meeting the targets rather than arguing about the appropriate monitoring process.



How does the local authority collect payment for the after survey?

To simplify this process we have suggested that the local authority collects the money for the monitoring upfront as part of the S106 agreement.

Otherwise there may be difficulties in securing payment at a later stage.



How many travel plan surveys are likely to be undertaken?

It really depends how quickly the standard approach to assessment is adopted by local authorities across the UK, i.e. planning applications are only approved subject to meeting specific targets for mode share and trip rates that are measured using the standard. In theory, given the present number of relevant planning applications there could be anything up to 3,000 surveys undertaken per year. Initially, in the first few years, it is expected that up to 50 surveys per year will be added to the system and this will build steadily. Replicated throughout the UK and Ireland this will generate a substantial amount of comparable data, invaluable for future planning applications.


Can the standard be used to keep track of travel plan implementation across a region?

No. It is not intended for this purpose.

Local authorities do need to keep better records of the development-related travel plans and keep track of those that have monitoring requirements. This could be done using a GIS system or a bespoke system, such as iTRACE used in London.


Will TRICS® undertaking counts cause delays to the local authority receiving data (as it would normally come direct to us)?

Not at all. The standardised approach to assessing travel plan impacts will actually speed up the process of receiving data. It will also ensure the data is robust and independently validated, before providing it to the local authority and the organisation responsible for delivering the travel plan. The data collection will be programmed into a schedule of surveys that is undertaken by a panel of accredited suppliers. Dedicated resources will ensure that data is supplied on time and to a consistent high quality. The information will be accompanied by an independent summary report prepared by TRICS®. This will speed up not only the process of data collection but also negotiations between parties as it will avoid potential for bias due to vested interest.


Will there be any scope to do fee deals if more than one survey needs to be undertaken (for future monitoring purposes)?

Yes, it will be possible to offer a discount if the survey needs to be repeated, particularly if the site audit undertaken to establish the survey requirements remains valid. Discounts have already been negotiated with the data collection companies which means that surveys commissioned through TRICS® are substantially cheaper than those commissioned independently on an ad hoc basis.


Can the market really stand paying Local Authority monitoring fee's AND measuring fee's to TRICS®?

Increasing numbers of local authorities are now charging a monitoring fee to pay for maintaining a database to keep track of travel plans required. Many do this in-house as part of their development control requirements. Most local authorities promoting the implementation of travel plans already require an organisation to pay for a survey to collect data to demonstrate that they have met their travel plan targets. The UK Standard for Assessing Travel Plan Impacts simply requires this data to be collected by an independent third party and offers attractive economies on other alternatives. Organisations are therefore already paying for the data and it is not a new charge. There is general market acceptance for local authorities to charge for both in-house systems to keep track of planning requirements and the assessment surveys.

SUBMIT ANOTHER QUESTION TO OUR FAQ PAGE>

TRICS now live on the web measuring travel plan impacts Guide to Transport Assessment new 2008(a) demo TRICS/RTPI Transport & Development Conference